Our Q1 starts in April so I need to be able to change the quarters in the JIRA roadmap function.
Hi @Zahra Murji
At present, this isn't possible. Quarters are set to match the calendar year.
Although these aren't listed as Q1, Q2, etc - if your Q1 starts in April, doesn't it still match the calendar year quarter segments?
Or it looks like this suggested feature - JSWCLOUD-18385 - covers the need to flex the months related to each quarter. You could vote for this issue and follow it to see if it gets implemented.
Ste
It seems like 18385 is what we need. Have made a comment there