I've got a plan in JIRA Portfolio tied to many JIRA projects. Today I did an 'update from date..."
It seems that for many JIRA issues were updated with incorrect original and remaining estimates.
I did not think what I was doing would push any updates from JIRA Portfolio or change any estimates.
I DID NOT do a "planned update to project(s)..."
Under plan config, data, sync: Update estimates is set to off.
Under keep backlog items in sync, Summary, Description, and Estimates fields were checked. Did having estimates checked cause this?
In short, my goal is to only go in one direction - Bring updates from JIRA to JIRA Portfolio (not vice versa).
I only want to update the work logged, status change, and progress. I don't care about updating the estimate if it might cause issues like this.
Can anyone advise?