Would there be anything to consider if we change current PI and iteration (last iteration) end dates?
Thank you.
Hi Reddy!
So sorry for not getting you a response sooner. Changing the PI and Sprint Start/End dates may impact how some data displayed in reports, but that's about it. For example, the Scope Change report pivots off of the PI start and end dates, so if you moved either date the report data could change (e.g. if you change the start date to be earlier than originally planned, the report might show a large influx of work after the PI start).
If you have Jira and Jira Align integrated, here are a few things you need to make sure to do to ensure data syncs up properly:
I hope this helps!
Thanks!
Mark