My ART has successfully used Jira Align for one remote PI Planning so far. As the RTE, I am continually looking for ways to improve PI Planning, and I have four questions about Jira Align related to this:
1. Is there a way to measure the % of points spent on Business Features, Enablers, and Tech Debt/Maintenance at the ART level and the team level? We want to start using a capacity allocation policy to guide how we allocate our effort across the ART and need a way to measure it.
2. Is there a way for teams to present their capacity and load for each iteration during PI Planning?
3. For a new team that doesn't have a velocity yet, or a team whose velocity is expected to change due to a change in team members, is there a way to enter a team level velocity override to use in PI Planning?
4. Does the Innovation and Planning Iteration contribute to a team's average velocity? Is there a way to exclude it?