We use JIRA and eazyBI in our projects. For issue explanation sake, Ill use simpler names. Teams are A , B, C and In JIRA, common board that we use across all teams is "X"
Teams are free to create their own sprint boards such as A, B and C
We have eazyBI as an add-in in JIRA and I have created a dashboard with graphs (velocity, sprint success and stability etc) which are sourced from eazyBI
For unknown reason, for a specific sprint onwards (example sprint 232 onwards) , all the sprints are mapped to sprint board A instead of X
Hence, In team B's dashboard only when I change the sprint board name from X to A, then I see all closed sprints 232 onwards, and not otherwise
Could anyone please tell me the possible reasoning and solution for this?