Hello,
We started using estimation from the 2nd sprint of the team and although that I get the completed story points in the report I do not get the committed.. Any idea on what we are using wrongly?
Hey! I'm having the same issue, did you figure it out?
I did some changes in the board configuration and it finally worked. I set estimation statistic to Story Points..
Thanks! We did have that set though, so ours is probably smth else
I already had that configured and I am still only getting the green bar and no commitment data for velocity. Does anyone know why?
We updated the version of our server jira and now everything is fine!