I went through a bunch of FAQs on the board. I see the debate about sub-task estimates not rolling up, but my need is simpler - to see the time spent on sub-tasks roll up to the user story, then show on the card.
I see the story details page showing the sub-task estimates, remaining time and logged time. The sub-tasks themselves are complete and on the board, their cards are showing the 'time spent' field (I activated that through the board configuration).
But on the user story card the time spent shows as 'None'. I would like see the rolled-up time spent in the user story card. Am I missing on some configuration?
BTW, other stories (where there are no subtasks), the card reports the time spent accurately.