Hello,
On 7th of January i did a Re-index due to changes being made in some of the projects. New tickets with new numbers started showing up in several projects but with the dates showing the 1st, or back in December. None of these tickets showed up before the re-index.
So this bring up 2 main questions:
1) What can cause this to happen?
2) is there a way to check for this short of doing a re-index. Either a check in Jira or running an SQL report? I'm assuming that i would look for NULL key values but it's hard to test.