Hello,
We just completed Sprint#4 for our Inspire Wall project and when I look at the Burnup Report the sprint completed line says we completed 53.5 out of 68 story points however the Velocity Report says that we completed 53.5 out of 74 story points. Why is it different?
Hello @Kyle Ray
The difference between the total 68 story points, presented in the burndown chart, and the committed 74 story points from the velocity charts come from the following: