Hello all,
I need your help with an issue I'm facing in Jira.
A user tries to perform the transition from In Progress to Resolved (No Fix Delivered) using the Bulk change option.

According to project's workflow when if the resolution = Duplicate we have to set the 'Linked Issues' field to Duplicates and type the correlated issue key in the 'Issue' field.

The error is the result of a scripted validator we use.
I would like to ask if there is an option to enable "Linked issues" field in bulk change operation or if there is any workaround for this.
Jira v. 7.9.2.
Thank you!