Scenario:
You move a story or series of stories from Project A to Project B.
Each story was linked to both a fix version and an Epic in Project A
During the move: You are asked what version the story should be in in Project B (Awesome)
The stories move over successfully and are linked to the proper Fix Version (Awesome)
However - the Epic that the story was linked to in the original Project A remains tagged in the story. However there is no way to see this epic in the backlog. You have to create a new epic and tag each of the stories with that new epic. Why?
In short, why does the Epic carry over and not display? Why is the user doing a move not asked what epic to move the story to like they are asked for version? Why can't you create an epic on the fly in this scenario? Short of changing the JQL query used by the board, why are epics left in the dust in this scenario?