Hi,
I have a Release Burndown that is predicting that my team will complete all issues within 2 sprints, based on 23 points per sprint and there are only 33 points left to burn.
However(!) when I look below at the incomplete issues section, it is indicating that I have 53 points left to burn.
funny enough, my Version report is including the 53 points.
Why does it happens, why there's a discrepancy?