Hello,
It's my first time setting up the project from ground up, while worked as scrum master before with project already set up.
What I want to create is a hierarchy in which I can simply track and count the hours.
The hierarchy that I have in mind is simple:
Counting the hours of sub-tasks in tasks of course work automaticly. What I want is to for example take a look at story and see the sum of estimated, remaining and tracked hours of all the tasks linked to it the same way as it works for task and sub-tasks.
For now I set this hierarchy up so that:
- stories have epic links to epic
- tasks have relates to links to stories
- sub-tasks are sub-tasks of tasks (obviously)
Is there a way to set something like this up in JIRA?