I'm asking that silly question as I have started a sprint and 2 of the issues initially added are considered as "added after sprint started" even if that is not true... Anyone knows what is the logic behind in jira?
Hello,
I believe you should compare the date, when the Sprint value was set for the issue, and the start date of the sprint.
You can find the date, the Sprint value was set, in the Issue History.
yeah it seems that the dates of start sprint are not well set up...
Really weird as I moved the stories to the sprint and then I click on start. I guess the start date in the sprint was not correct....