Show priority for sub-tasks list (from task view)

Colden Rouleau
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 23, 2018

I want to show priority on sub-task lists.

 

Example:

I have a task named "Make Peanut Butter and Jelly Sandwich". It has subtasks:

  1. Buy Peanut Butter (we're out!) [priority: Critical]
  2. Get two slices of bread from stock [priority: Major]
  3. Apply Peanut butter to one slice [priority: Major]
  4. Apply jelly to the other slice [priority: Major]
  5. Add banana slices to the peanut butter slice [priority: Trival]
  6. Final task: Connect halves together to make a sandwich [priority: Major]

 

However, if I'm viewing the "Make Peanut Butter and Jelly Sandwich" parent task, while I can see all the subtasks together in a list, I can't see which one is more important. It's probably a good idea for me to go buy peanut butter before I do anything else - it's a high risk task! What if I tried to make the sandwich late at night after all the stores were closed? It would be a project failure. In contrast, the banana slices are optional, and so less important.

 

What I'm talking about looks like (heavily sensored)jira.png

3 answers

2 accepted

3 votes
Answer accepted
Aleksandr Zuevich
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
May 23, 2018

Hi Colden, 

It's also supported for Jira Cloud. You should go to General Configuration -> Advanced Settings:

screen.PNG

2 votes
Answer accepted
Carlos Garcia Navarro
Community Champion
May 23, 2018

Hi Colden,

Are you using JIRA Cloud or Server?  If you're in Server you may find some tips here:

https://community.atlassian.com/t5/Jira-questions/Add-column-to-list-of-Sub-Tasks/qaq-p/38554

More specifically, you can go to Administration --> General Configuration --> Advanced (button at the bottom of the page) --> jira.table.cols.subtasks, and add the column you need

If you're in the Cloud, I don't think this is supported.

Carlos

0 votes
Kenny
March 6, 2019

I can't seem to find this setting in the most recent version of Jira, any pointers?

Thanks!

Aleksandr Zuevich
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 7, 2019

Hi Kenny,

 

Please specify exact version of Jira.

Like tamara_davis likes this

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events