In Our Scrum Board we are not using Stories. We are using Tasks (Not sub-task).

We estimate TASKs in story points. Will JIRA show the velocity chart?

2 answers

1 accepted

0 votes
Answer accepted
Arnelys March 5, 2025

Yes, but you have to have more than one closed sprint because the velocity of a sprint is calculated by averaging the total estimates completed in the last sprints

0 votes
John Funk
Community Champion
October 19, 2025

Hi Gyanendra - Welcome to the Atlassian Community!

I am marking Arnelys's answer as accepted. Please let us know if you have more questions. 