Does JIRA calculate velocity for TASKS (not Subtask)

Gyanendra Agrawal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 5, 2025

 

In Our Scrum Board we are not using Stories. We are using Tasks (Not sub-task).

We estimate TASKs in story points. Will JIRA show the velocity chart?

1 answer

0 votes
Arnelys March 5, 2025

Yes, but you have to have more than one closed sprint because the velocity of a sprint is calculated by averaging the total estimates completed in the last sprints