When moving several Task issue types (each with several Sub-Tasks) to a new Jira project, the sprint value is only partially carried over to the SuboTasks.  Not sure why. 

NOTE:  All items are in CLOSED status and sprint value is for a closed sprint.

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 1, 2022

Sub tasks do not have sprints, so I'm not exactly sure what your problem is here.  Could you explain more please?

Deanna Jones
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 3, 2022

Sub-Tasks can be assigned to a sprint, so a bit confused -- at least subtasks in my Jira board can be assigned to a sprint.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 3, 2022

No, they can't.  A sub-task is only "in" a sprint as part of its parent issue.

Unless you've defined your own Sprint field, which won't be the one Jira is using for the board.