Hi, everybody.
Would like to know if JIRA Service Desk provides a way to prioritize tickets based on global contract SLA. I mean say there's two customers each with a different contract terms. Customer A contract states 80% of tickets should be resolved within 16 hours. Customer B contract states 70% of tickets should be resolved within 8 hours.
Tickets for both contracts are served by the same staff.
Say so far 90% of Customer A tickets have been resolved fulfulling the SLA, but for Customer B only 60% of tickets so far have been resolved fulfilling SLA. So I can afford Customer A tickets not to fulfill SLA as long as ratio doesn't fall below 80%. That way I can prioritize Customer B tickets and hopefully achive 70% or higher fulfillment.
Furthermore we might factor in the penalty stated by each contract to determine ticket prioritization in order to minimize or eventually eliminate penalty.
Hope you can comment on this.
Thank you all.