How do I change what columns are displayed in the Jira Advanced Roadmaps Gantt chart on my Confluence page? I want to show Start Date/End Date, not Target start/Target end, as my teams use the former two fields in their Jira issues. Thank you!
Hi @Jeff Davis
The view use in the Confluence macro is the one you have when you create the Share Link. So, you can create the view you want, create the share link and add the link in the confluence macro.
Regards
@Florian Bonniec thank you. That worked.
In case anyone is unclear what I did, I deleted the roadmap in the Confluence page, went back to Jira, ensured the roadmap displayed the information I needed it to display, recreated the link for Confluence from the Share option, and added it to Confluence.