The 4 week sprints I have created on my team based software plan and assigned to every issue do not appear on the associated plan I created. I have also created a team and assigned the team to every issue on my project and to the plan. The plan is showing projected sprints and recognizes my sprints as EXT, which doesn't make sense. I have associated the team to the project and I have set the team's sprint cycle to 4 weeks as well. I'm suck.
Out of curiosity, in your plan configuration, is your team's issue source set to a board or a project? To see sprints, you need to use the board as the issue source (since that's where sprints are created and live).
Eddie
Welcome to the community.
Can you show some screenshots of the plan and the configuration and of an issue where the team field is set?