I am using Advanced Roadmaps since 2 years ago. At the beginning tool worked perfectly for me, but in the mid of last year something was changed and tool cannot support our needs any more.
I am curious can I configure Advanced Roadmaps to work as before?
What I identify that was changed:
- Capacity planning is applicable only from today. Bars (for capcity planning) which are in past are empty, even if start date is in past and if some work was done in past (I would expect that estimation will be equally split from start to target date, not from today till target date)
- Even if I have target date defined, load per weeks will not be split equally from start to target date. Advanced Roadmaps ignores my target date if team has capacity to finish ticket earlier.
Do you have advise what is the best way to use this tool now with those changes?
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.