Using different due dates for invidual members

Deleted user January 5, 2018

Is there a way to set different due dates for members on one individual card? If two members are working on one card, but one due date is later than the first, is there a way to set a second due date? 

1 answer

0 votes
Mike
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 8, 2018

Hi Margie,

 

Not exactly—a Trello card only supports one official due date at a time, but one option is to use the Custom Fields Power-Up to add additional date fields to any card. These won't appear on the calendar view, however, and won't generate notifications, so they don't work quite the same way!