How to add dates to next Gen JIRA roadmap ?

I am new to JIRA roadmap. I would like to add the dates for each of the epics. In the roadmap view, I see the dates only when I hover on the epics. Hence, it's impossible to know the dates when I export the Roadmap. 

Can someone please let me know how can I display the dates on the Roadmap itself ? 

1 answer

1 vote

Hi Hema,

you can't make the dates visible on the roadmap itself for each epic at the moment.

However, if you view or export roadmap in "Weeks" then you'll be able to see where the epic starts and ends as dates

Screenshot 2019-11-11 at 17.21.14.png

Otherwise, the start and end date are visible in the field at the bottom of each epic.