An admin user cannot prioritize the backlog

Audrey March 19, 2013

One of our admin users (who is also the product manager) is unable to prioritize the backlog. He receives an error message that he doesn't have the ability to do this with his role. He has to be able to prioritize the backlog as the product owner. Please advise how to fix this problem.

Thanks.

1 answer

1 accepted

2 votes
Answer accepted
JoanneA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 20, 2013

Hi Audrey,

He will need Schedule permission for the project in question in JIRA to be able to rank issues.

If you are a JIRA admin, you can set this up - here's more details of how to do it:

https://confluence.atlassian.com/display/JIRA/Managing+Project+Permissions

Audrey April 4, 2013

Thank you! Very helpful.

Suggest an answer

Log in or Sign up to answer