Why does shared teams not cut across two plans for capacity

I have shared teams across two plans.  The plans are not showing over allocation in capacity when using the same teams in the two plans.

  • Shared Team 1 has 400 hours of capacity per sprint.
  • Plan 1 has sprint 1 allocating 400 hours to this shared team
  • Plan 2 has sprint 1 allocating 400 hours to this shared team

There is not any call out of over capacity between the two plans even though technical the team is now working 800 hours when you combine the two  plans for sprint 1

0 answers

Suggest an answer

Log in or Join to answer
Community showcase
Josh Frank
Posted Dec 01, 2017 in Portfolio for Jira

Portfolio for Jira: Share your tips!

The Portfolio for Jira team wants to hear from you. Share your top tips for building a great Portfolio for Jira plan for a chance to win some Atlassian swag.  Do you structure your teams i...

568 views 6 8
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot