How to automate the complete movement of a task from one project to another?

Dmytro Shaforost May 17, 2021

It is necessary to set up automatic movement of a task from one project to another when an event occurs, so that attached files are copied.

1 answer

1 accepted

3 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 17, 2021

Moving an issue is not a trivial action - the project and issue type are fundamental structural attributes of an issue and hence require a load of checks and usually updates in order to change the shape of the issue from the old to the new.

I would want to question why you are moving issues between projects.  It can be a perfectly valid thing to do (mostly when housekeeping or correcting things raised in the wrong place), but if you are trying to do it as part of a standard process flow, then you have a broken process, and you should look to revise that so that you don't move issues.

Dmytro Shaforost May 19, 2021

@Nic Brough -Adaptavist- Thank you for your answer. We decided to revise our processes.