How does Jira Agile calculate the days in a sprint?

Rich Scire November 5, 2015

I have a sprint that has the following dates:

    Start date: 5/Nov/15 12:00 AM

    End date: 19/Nov/15 11:59 PM

When I start the sprint, it says that the sprint has 10 working days even though the dates encompass 11 working days. Does it not count the final day? It looks like this has something to do with the time since if the times were the same, then 10 working days would be correct. Can anyone offer a definitive explanation?

 

I appreaciate any help given.

 

Thanks,
Rich

2 answers

0 votes
Rich Scire November 6, 2015

The only non-working days are the weekends. It really looks like it doesn't account for the time portion of the date. So, Tuesday->Wednesday is counted as one day even if Tuesday 12:00 am -> Wednesday 11:59 pm is two days (minus 1 minute). Or maybe since 12:00 am to 11:59 is less than one day, it's not counted.

0 votes
Timothy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 6, 2015

Can you check your Board's Configuration if there is a non working day applied?