How does Jira Agile calculate the days in a sprint?

I have a sprint that has the following dates:

    Start date: 5/Nov/15 12:00 AM

    End date: 19/Nov/15 11:59 PM

When I start the sprint, it says that the sprint has 10 working days even though the dates encompass 11 working days. Does it not count the final day? It looks like this has something to do with the time since if the times were the same, then 10 working days would be correct. Can anyone offer a definitive explanation?

 

I appreaciate any help given.

 

Thanks,
Rich

2 answers

0 votes
Timothy Chin Community Champion Nov 06, 2015

Can you check your Board's Configuration if there is a non working day applied?

The only non-working days are the weekends. It really looks like it doesn't account for the time portion of the date. So, Tuesday->Wednesday is counted as one day even if Tuesday 12:00 am -> Wednesday 11:59 pm is two days (minus 1 minute). Or maybe since 12:00 am to 11:59 is less than one day, it's not counted.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,760 views 11 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot