How does Jira Agile calculate the days in a sprint?

I have a sprint that has the following dates:

    Start date: 5/Nov/15 12:00 AM

    End date: 19/Nov/15 11:59 PM

When I start the sprint, it says that the sprint has 10 working days even though the dates encompass 11 working days. Does it not count the final day? It looks like this has something to do with the time since if the times were the same, then 10 working days would be correct. Can anyone offer a definitive explanation?

 

I appreaciate any help given.

 

Thanks,
Rich

2 answers

0 vote
Timothy Chin Community Champion Nov 06, 2015

Can you check your Board's Configuration if there is a non working day applied?

The only non-working days are the weekends. It really looks like it doesn't account for the time portion of the date. So, Tuesday->Wednesday is counted as one day even if Tuesday 12:00 am -> Wednesday 11:59 pm is two days (minus 1 minute). Or maybe since 12:00 am to 11:59 is less than one day, it's not counted.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

82 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you