How can I add a sprint before an existing but inactive sprint?

I have an existing sprint (lets call it sprint 1). Then I created 2 other sprints (sprint 2 and 3). Is there a way I can create a sprint before sprint 2 (let's say sprint 2.5) ?

2 answers

0 votes
Janet Albion Atlassian Team Sep 17, 2013

Hi Mohit,

You can create multiple inactive sprint in your Scrum board. Eg: Sprint#1 is current active sprint. So, do you by chance want to be able to arrange the sequence of the sprint in the planning board as per requested at https://jira.atlassian.com/browse/GHS-7470 ?

Yes this is exactly what I need. Will you be building this feature?

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

500 views 1 15
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot