moving a task from current to previous sprint

sari sasidharan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 13, 2021

How can I move a user story from current sprint to previous sprint as those tasks are already completed in previous sprint.

3 comments

Comment

Log in or Sign up to comment
Anita Kalmane
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 13, 2021

You can manually remove the story from the current sprint.

For adding it: If it wasn't added to the previous sprint, I don't think it's possible to do it anymore though.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 13, 2021

There is no good reason to add an issue to a finished sprint, and hence Jira doesn't support it.

What are you actually trying to achieve by rewriting history here?

Sebastian Szymanek April 19, 2022

I have tired bulk option => edit issue => sprint and it worked. 