moving a task from current to previous sprint

How can I move a user story from current sprint to previous sprint as those tasks are already completed in previous sprint.

3 answers

I have tired bulk option => edit issue => sprint and it worked. 

0 votes

There is no good reason to add an issue to a finished sprint, and hence Jira doesn't support it.

What are you actually trying to achieve by rewriting history here?

You can manually remove the story from the current sprint.

For adding it: If it wasn't added to the previous sprint, I don't think it's possible to do it anymore though.