How do I start a second sprint in the same project?

We want to start a second sprint while the first sprint is finishing up

1 answer

Hi Joe,

May I know which GreenHopper version are you using?

Anyway in the latest GreenHopper version, you should be able to enable the "Parallel Sprint", which basically allows you to start multiple Sprint at a time. Kindly refer to the following documentation for more info on this:
- https://confluence.atlassian.com/display/GH/GreenHopper+Labs#GreenHopperLabs-ParallelSprints

I hope that this will help!

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 14, 2018 in Agile

Marketplace Technical Collection Pages

You might have noticed something new on Marketplace in the last several months which was the addition of our new collection pages. We heard feedback that it can be hard to browse apps in Marketplace ...

63 views 0 4
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you