No sprint in progress or old, appears for selection in the jira portfolio.I was able to use it previously for a sprint but now I am no longer able to see for the other sprints.Follow the print with the evidence below.
Hi, Kleber
If you want to see your existing Sprints from Jira in Portfolio, you need to use the Board associated in those sprints as Issue Source in your plan.
Since sprint are not dependent on projects, if you use a Project or Filter as issue source, Portfolio won't be able to replicate them to your plan.
Let me know if this clarifies! :)
Gabi
I am having the same problem... issue sources (projects and boards) have been selected... still unable to view the active sprints??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi!
Remember that you need to group by Team or Sprint and check on "Show capacity on timeline"
In this link you have the official information about this https://confluence.atlassian.com/jiraportfolioserver/displaying-capacity-in-a-plan-974360323.html