Is there a point to populating the team members in an Advanced Roadmaps team?

Rafe Nussey
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 24, 2020

With the changes made to AR, i.e. skills and working hours no longer being relevant, I assume the only value of a team in AR, shared or otherwise, is to assign work, sort issues and of course to measure team velocity - nothing more granular than that?

If this is the case, is there any point in populating the members of an AR team except as a reference to who is on the team?

1 answer

1 accepted

2 votes
Answer accepted
Roi Fine
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 25, 2020

Hi @Rafe Nussey ,

Your assumption is correct adding members to a team is mostly used for reference. If you need to plan team capacity when people join, leave, or on holiday you can adjust the capacity in the sprint/iteration flyout. Details how to can be found here.