One of the teams I am working with has a stable velocity, but will be having a specialist join the team for a few Sprints to address some specific (related) work.
The team want to show increased capacity/velocity in Portfolio to reflect the work they are doing, but they also need to velocity to drop back down after the specialist leaves the team to ensure they don't take on too much work for later releases.
In short:
- Specialist's Stores need to be estimated (in points)
- Team capacity needs to increase while the specialist is with the team
- Team capacity needs to drop back to former level when the specialist leaves
What is the best way to achieve this in Portfolio?