Hello,
It's noticed that changing Target Start/End dates in a roadmap instead in a Jira ticket breaks their synchronization - as of that moment the dates changed in a ticket don't affect them in a roadmap.
Is there a way to return the synchronization back?
BR,
Norman
Hi @norman and welcome to the Community!
Can you verify if you have committed the changes you made in the roadmap to Jira through review changes / save to Jira? Maybe you ended up with concurrent updates, where you may accidentally have updated the same data on both ends.
I would dare to try removing the dates from the roadmap or reimporting your issues to your plan through configuration / issue sources.
Hope this helps!
How do I show my linked stories to an Epic bar chart and target or Start/due dates in roadmap. Presently my roadmap shows the Epic and it linked stories but not status bar over dates
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.