Project A is my engineering project team.
There are Epics, Stories, Tasks linked to other Project B and Project C dependencies (who have their own fix version and flows).
1. How can I focus the gantt/roadmap bars for Project A tickets?
- If I don't, the list of tickets will be very long.
2. How do I ensure all project dependencies are shown across Project A/B/C or other projects under the Dependency tab?
3. Will changes I make in the plan (drag and drop/rank, drag date bars) impact Project B and C issues? (I am not the owner for those teams)