When creating my plan and it asked which Releases and Issues I want to include, I marked some as not part of the plan, but, now want them included.
How do I add back in a Release or Epic from JIRA into my plan?
Hi @Mike Lemmon ,
From your plan, get into the plan configuration by clicking the cog wheel next to your plan's name.
In the left hand menu bar, under Source Data you should find the option issue sources. It will show you an option to Edit issue sources.
Clicking that button will take you through the wizard that you used initially to import your data. In the different steps you will be able to select the items you removed/excluded earlier.
Thanks Walter .. this works .. Perfectly Just getting into using Advanced Roadmaps .. I will likely be pestering you for more insights .. soon.
Thanks again, have a great day.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ah.. just found this question asked and answered before .. thanks to the .. Community..