Dependencies change Start and Due date based on blocked issue changing dates

Lance Wadman February 14, 2022

I have a number of stories that are dependent on other stories.  My dependencies do not have due dates or start dates but would start when their dependency is finished.  I am trying to figure a way that if the first story slips how can the other stories dynamically adjust based on the change date of the first one?

1 answer

1 accepted

4 votes
Answer accepted
Curt Holley
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 14, 2022

HI @Lance Wadman 

Welcome to the community!!

As far as I am aware, Advanced Roadmaps will give you a warning about that kind of thing, but someone has to do something about moving them (manually).

If you wanted that to happen automatically, it can be done via Automation for Jira.

High level, unconditional example of how to automate:

hla.png

Lance Wadman February 16, 2022

Thank you for the response.  I will look into automion for this change field

Mohamed Fouad
Contributor
June 16, 2022

Hi @Lance Wadman just confirming if you tried above automation logic, as I have same query like you. 

Brad M
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 11, 2023

Seems like more work than should be needed for this... thumbs down JIRA

Like # people like this

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events