AMIT GULATI June 14, 2018

In JIRA Portfolio, it allows you to put the story points for epic as well. However, for scheduling it only picks up the story points of stories within that epic. 

Is that the right understanding?

If so, what role does the epic estimate play in deciding the timelines? 

1 answer

0 votes
Shannon S
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 22, 2018

Hi Amit,

The estimate on the Epic's story points do matter, and help with scheduling. However if you're at Story Level only, you won't see a difference.

Can you confirm what situation you're seeing exactly and what version of Portfolio you're using?

Regards,

Shannon