You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
We are not a fully SCRUM team but we are trying to follow agile principles:
- 2 week sprints to iterate and track work
- Story points to estimate
Our manual calculations give us estimated finish milestones such as 5/5.
1. Should I use "target end" or "due date" of 5/5?
2. When I tried Due Date, the roadmap view did not show 5/5
3. How does the roadmap generate dates from story points?
Hi @Bea Tea
How does the roadmap generate dates from story points? it doesn't.
The timeline data is generated by the date fields you choose to use in your Plan.
Disclaimer: I'm talking about Cloud AR...am uncertain regarding non Cloud versions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks @Curt Holley Maybe I read the info/tutorials wrong. I thought that it could generate some timelines based on Story point estimates.