Maximum assignees per story set to 1, but portfolio still suggests 2 ppl to work on the story

Hi Community, 

I'm on newest portfolio version 2.9.0, and with Jira software server 7.4.3.

I've set "Maximum assignees per story" to 1, and set a story manually to a certain sprint (instead of "calculate").

Very strangely, after calculation, Portfolio still suggests me to assign two ppl on that topic (pls see pic below).

Could you explain me why and how should I really restrict it to one assignee per story?

Thanks,

Onyx

 

 

_t.useScrumMethod_2017Nov - Portfolio for Jira - Jira 2017-11-30 17-38-54 zzScShot.png

1 answer

0 votes

Hi Tommy,

I did some research and haven't currently found a solution to this. There have been discussions on this in the past and it looks like a Suggestion was posted in that post that you can find at JPOSERVER-1741

In addition, I found another Suggestion at JPOSERVER-1502.  Please vote on both of these issues and add your use case to the comments to add impact to help get this feature implemented.

Cheers,

Branden

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira

Online AMA this week: Your project management questions answered by Jira Design Lead James Rotanson

We know that great teams require amazing project management chops. It's no surprise that great teams who use Jira have strong project managers, effective workflows, and secrets that bring planning ...

208 views 1 6
Read article

Atlassian Community Events