When i create a new plan and import data from Jira, the information about assigned team member is not set when story is marked as done.
This it how it works or am i missing something?
Scheduling options
Assignee import level: Sub-task
Maximum assignees per story: not set
All other options: on
Your understanding is correct, Portfolio will not import the assignee on closed issues.
The reason is that the assignee import happens when Portfolio calculates the optimal way to resolve an issue (Who should work on it and when), if the issue is already resolved then nothing will be calculated for it!
Cheers,
Thomas
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.