Jira Portfolio Capacity calculation

Teija Kurttila May 29, 2018

A question for Jira Portfolio use:

How does Portfolio calculates team capacity for future capacity? Our team sprint capacity is 348  hours per sprint (2 week). Portfolio looks like this for future sprints. Why isn't the sprint (2) full instead it calculates work  also for sprints 3 to 6? We don't have any dependencies in our stories. Shouldn't almost all capacity be on the sprint 2?2018-05-29_12-03-05.jpg 

1 answer

0 votes
Deleted user May 29, 2018

Hi @Teija Kurttila,

The scheduling behaviour takes into account multiple data points within JIRA. This could be why sprint capacity could be left over.

See a similar question with a response from an Atlassian Team member. 

Hope this helps