Is there any way to update 'Capacity' within a specific sprint in Portfolio?

Hi all,

I'm monitoring each team member's scope vs capacity (workload) with a portfolio capacity view.

But I realized the 'capacity' parts here is not affected by daily time progress.

It seems that the capacity used for calculation is based on the Sprint 'Total' capacity not Sprint 'Daily updated' capacity.

For example, lets' assume that my capacity was 160hrs = 8hrs/a day x 4 weeks(20days) when I started a October sprint. After two weeks later, the updated 'capacity' is supposed to be 80hrs (because I only have two weeks left to finish my works assigned to this October sprint) to calculate the exact overload comparing 'Remaining hours'.

Work remaining is reduced daily, but why capacity is still the same as the time to start the sprint?

Is there any way to modify 'capacity' reflecting time progress?

 sprint.PNG

Thank you!

Kind regards,

Jenny

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,290 views 19 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you