How to spread workload for a specific skill over multiple sprints?

Context:

  • 1 scrum team
  • 3 stages:
    • Analysis
    • Development (skills: JS, functional testing)
    • Testing
  • 1 project with 45 MD JS and 7,5 MD functional testing (in development stage)

Problem:

When calculating the planning, the workload for functional testing is fully planned in the 1st sprint while the development workload is spread over multiple sprints.

Preferred scenario:

I would like the functional testing to be spread over every sprint where development is planned. I doesn't make sense that the testing is fully done in the first sprint.

A possible option could be the reduce this functional tester's capacity in the team, forcing Portfolio to spread the workload over a longer period of time. However, if I do that, I don't get a realistic situation because in reality this functional tester would be idle.

 

I'm just starting with Portfolio and I'm trying to implement it for a much bigger team and more complex situation. But making small steps..

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,638 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you