You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Dear community,
I have created a cross-project release (CPR) with a fixed end date. However, after finalizing the scope the date of one of the projects has moved past the end date I have specified (with a red flag indication). Obviously Portfolio flexes the time edge out of the resources-scope-time iron triangle.
How can I fixate the time edge and make it flex the resource edge? In other words, how can I configure Portfolio so that the end date stays fixed while the teams' capacity gets overloaded?
Thanks,
Michael