It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

How can I enter the task progress by 'Percentage' & track overall project progress by % using JIRA?

Hi All,

I am new to JIRA and trying to explore Project Management using JIRA. I have a query w.r.t tracking the project progress. I see JIRA provides option to track the project progress using time tracking(I use Big Gantt). However, is there an option by which we can update the task/sub task progress by %, and the total project progress gets calculated based on that. For example, a task(within) is assigned to a user with 10 days of duration. On the 5th day after the task started(the task is supposed to be 50% complete by now), the user updates the progress as 40%. The overall project progress should now fall behind from what is supposed to be as of today. The whole idea is instead of entering the time spent on task, update the same by % and calculate overall project progress.

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,645 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you