Could you compare the JIRA licence with the plugin licence? I mean the text beneath them - does the JIRA one say something like "Commercial licence" and the Automated worklog says "Development"?
-
Did you set up and test a mail server with the system? If not, then that will explain why you don't get any emails. Anyway, try https://confluence.atlassian.com/display/JIRA/Retrieving+the+JIRA+Administrator
-
Yes, you can put "conditions" on your workflow transitions. Ones like "user must be in the role of PM to use this transition". That will simply stop your testers making mistakes, so the PMs won't have to move the issues. Start with a look at…
-
There's nothing to change settings for. The code required to expose this to REST simply isn't there.
-
REST does not currently expose the "add option to list" functions available to Jira admins. A few people have workarounds using post-functions or plugins that expose the function, and I'm afraid you'll need to code to do the same - it's not in the core, needs to be added.
-
The lock file is there explicitly to stop you running a second instance of Jira by accident. It disappears on shutdown to tell the next attempt to run that it is ok. The lock file sounds like it is working as intended. The usual cause of this problem is virus scanners (windows AV has to be implemented in an appallingly bad…
-
You're trying to do too many things at once. Removing the lock file only applies in certain circumstances, and it doesn't sound like you're in one of them. I'd try to start clean. Shut down Jira. Check it's all stopped with a basic ps -ef command (or digging through windows task manager if you're stuck with running it on…
-
You almost certainly hit "yes" when asked "would you like to watch this label". Click on "topics" above and you'll get a list of what you are watching. With handy little X marks next to them. (Give it a few minutes after belting a few of the Xs and it should stop emailing you...)
-
Well, I'd say it's very flexible, but that gives you complexity in using that flexibility. I also think "resolution is empty/not empty" is a poor way to do this particular function. It was fine in JIRA 1 when there was only one workflow, but now we have the power to define our own, it looks pretty daft.
-
Well, yes it does. If you removed resolution from the field configuration, then fine, it has nothing to work with so doesn't discriminate between issues with or without resolutions.
-
There's no debate to be had in this case. The choices available are1. Wait for Atlassian to change the "resolution = done" principle2. Rewrite JIRA and its applications and add-ons yourself3. Set resolution on moving into a "done" type status
-
Because JIRA bases open/closed on the resolution. It always has, and *everything* is coded on that It's not ideal, personally, I'd bin it and use a meta-status, but you can *not* ignore resolution.
-
Code. You'll have to hack the code providing the panels and filters. A far better alternative is to stop having projects that "don't use resolution", because you don't actually have them. You have projects that don't use resolution correctly and hence inadvertently break all the built in reporting (and it's not just JIRA…
-
Again, the project admin permission does NOT give the users access to permission or notification schemes. They only get version, component and user maintenance. Project Lead does not have to be filled at all. If you leave it empty, you can't take advantage of the automatic assignment by component stuff, but it really does…
-
I'm not sure why this is so hard. I know there's a lot of it, but I don't know why you keep going back and muddling up permission layers and simple fields. Each permission is separate. As I said already, you've got System Admin rights and Jira admin rights. That is controlled by global permissions. You don't want these…
-
The project lead is the project lead, I'm not sure how else to put it. You name someone as the project lead. They are responsible for the project. You can use that flag in other places so that when a project lead changes (Dave leaves, Bob takes over), you don't have to go through and change it, you just change the project…
-
Yes, you'll need add the permission in all of your permission schemes if you want it to be global though.
-
As I just said, project administrator is done in the permission scheme for the project. It's not global. Project Lead is a field that says "this person is the lead on the project". A common thing to do is say (in the project permission scheme, of course) "project lead has project admin rights", but it is optional
-
There are four levels of user in Jira * System admins - can edit ALL the system and Jira settings - specifically the stuff that is global and heavy - indexing, attachment paths, localisation, these guys can take the whole thing out. In Unix terms, they're "root" (and have all the rights of "Jira admins" below) * Jira…
-
Yup, just whacked a spammer, works well for me :-)
-
Kewl, I'll accept it as soon as I get to give it a go. Unless I really do need some new shoes ;-)
-
I wouldn't whitelist my links - it's all broken code, Doctor Who and pictures of kittens ;-)
-
So I was right? Yay :-)
-
Check your attachments settings - have you moved the attachment directory and forgotten to update the root of the attachments in Jira? Or the other way around? It looks like the first to me - there should really be more of a path than just /30303/<filename>
-
Yes, I find the language confusing as well, even the Atlassian stuff mixes up "issue type" (issue type) and "issue type" (standard/subtask).Sub-tasks are indeed issues in their own right, but they always live below a parent issue type and can't be created separately. Epics are also a bit confusing - with Agile, they are…
-
This is slightly confused by the language. JIRA ships with several issue types (bug, strory, issue, sub-task, etc) and Epic is simply another type. And you can add more. I think you're asking about the hierarchy, rather than the "issue types" (This is a matter of wording - issue type means something specific in JIRA-speak)…
-
Not easily. There's no grouping of issues like that available in the issue navigator.I've seen (and coded) simple workarounds, such as derived fields which always contain the parent issue (or parent/summary), so sorting by that first automatically works. But there's nothing simple built-in.
-
I think there's a bit of confusion here. JIRA's structure is not project -> subtask, it is project -> issue -> subtask, so talking about "parent project" doesn't make much sense. A subtask will have a parent issue which holds the subtasks, and is very associated with the subtask (because if you accidentally break the link,…
-
This is a slightly confused question. You use the phrase "resolution status", which is unclear in general, but when used in a Jira context, is dreadful. Resolution has a specific meaning. Status has a specific meaning. They are separate, distinct things which don't have any solid direct technical relationship. You can…
-
Sounds like your process isn't updating the index for the issues at the right time. JIRA will index on any updates made through the UI or REST, but if you're doing things with scripts or code, that needs to trigger the indexing too