No - if you have two Jira instances (sounds like you do, if you need to protect HR stuff from your main Jira admins), then you need two licences. Of course, if your HR department is small, a $10 license for a handful of users is not a huge expense... Atlassian are looking at bulk/site licenses as well, so in the future,…
-
Simple at first - create a permission scheme that only allow people in a certain group or role to browse the project. However, your comment about the Jira admin won't work. You can exclude the Jira admin, but they will ALWAYS have the ability to put themselves into a role or group that allows them access. There is no…
-
Custom fields - all the standard ones will work the way you expect, and there are some addons which provide more that are also available Pulling information into Cloud depends on "how". If you're simply using html to display stuff from other systems, then you can probably do it, but if you've got custom code doing it, then…
-
Same question and same user - https://answers.atlassian.com/questions/11457137/is-api-available-for-provide-jira-information-?src=email
-
Probably not - the html macros are rendered in the body, long after the header, and hence css, is loaded. You might want to guve us a bit more detail on how you've coded the macro, but I suspect the full answer is going to be that you need to put the css in the space rather than the macro, and 3.5 is too old to be…
-
There are no settings. That's the point of the answers below. You'd need to rewrite JIRA Software to enable this.
-
That doesn't really change my earlier answer - this is not an Agile way of doing things, so Jira-Agile doesn't do it. You're supposed to split or Epic-up your stories that don't fit in a sprint. Jira-Agile will roll over incomplete stories into the next sprint for you automatically, but it doesn't break the Agile principle…
-
But that means you can't rely on the sizing of stories to do sprint planning. Very simply put, you're throwing away planning, estimates and velocity. Stories shouldn't really cross sprints - if they're too big, consider making them Epics, or splitting them up. (Or the weakest option - extend your sprint or allow the story…
-
Mmm, you don't know that it's a bug. Can you reach Jira from your Fisheye server? On the right port? Can Jira be linked to other applications?
-
Ok, well, that looks like an SSL authentication error to me. This will either be a certificate problem (i.e. Fisheye doesn't have the right certificate or certificate authority to see your Jira) or an authentication error based on Fisheye or Jira not having the right to log into the other system.
-
You don't tell us what you are trying to "integrate" or where really. If it's two OnDemand systems that you own, then you need to talk to Atlassian OnDemand support. If not, and you want help here, then you need to tell us what the systems are and give us at least an outline of how they're configured and what you've done…
-
You set up both Jira installations to "create or comment" on issues by email. Then you set them both up to email each other. It's not really a synchronisation, it's really basic if you only have the standard mail handlers, but if you have the JEMH, you can make it quite close. For OnDemand though, you pretty much need to…
-
Those two are the best options for you at the moment. The only other approach is to write something yourself, using email or REST.
-
No. Your licence is for one server at 500 users. Atlassian are looking at site licences and will be introducing a 250 user licence level soon (I'm not sure what "soon" is though - I'd guess sometime between Summit and Christmas), but at the moment, you can't do this.
-
As many as you want. There's no way for a server to know when a client machine has a file open, so you have to have your users comminicate if they are going to try to edit the same files. There are a couple of ways to do "file locking" to prevent two users editing files - I've used Arsenale's Lockpoint in the past (there…
-
See https://confluence.atlassian.com/display/JIRA/Upgrading+JIRA and https://confluence.atlassian.com/display/DOC/Upgrading+Confluence
-
No, it's not. One of the main points of using labels is that they're pretty much unrestricted.
-
The system one should be appearing if you've added "time tracking" to the screen. And you've got time-tracking enabled. And (possibly) work log. I suspect we need to go digging through your fields. As a "clutching at straws" thing, could you have a look for "time tracking" and "original estimate" in the field configuration…
-
Ok, the Original Estimate is a built-in field (Although the toolbox adds extra things with funny names). To establish this, go to Admin -> Custom fields for the full list and look for "original estimate" in there. If you do NOT find it, it's the system one. If you do, then it's the toolbox one. After that, if it is the…
-
Ok what *type* of field is it? Can you confirm which screen and tab you have it on? And then we could use a look at your "issue type screen scheme"
-
Which screen are you looking at? If it's view, then the field needs to have data before Jira will display it (even if the field help er says it should appear, it needs data). Could you try a full edit on the issue and see if you are able to see it and fill it in?
-
Click on the field and change it. Or click "edit" and change the value in the edit screen.
-
Your boards are set to include issues from both projects. You need to change those.
-
I don't understand what you've done, why, or what you're trying to achieve by doing it. Some things jumped out as clear though: * Changing the project name in an export file is likely to break things unless you change the associated things. * "issues are interlinked" explains nothing about what you mean - links? Same…
-
This does not sound like the way JIRA behaves at all. Could you clarify something - when you say "project", do you actually mean "board"?
-
Confluence is a separate product, not part of jira or agile. Have you added it to your account?
-
Cancel what?
-
Short answer is "don't do it". You should not be even thinking about poking data into Confluence while it's running. "Refreshing the cache" would be a nightmare that involves rewriting core code. You could do it, but you'll need to retest all sorts of stuff, persist it through upgrades and frankly, there's far better ways…
-
I'm sorry, but the coffee is not working for me today, and I am not grasping what you are saying. Where, exactly, do you want to click to get the popup?
-
Ok, so you want a popup instead of going to a new page, but I'm still unclear on quite where you want the link to be placed. Can you not just put a hyperlink in the body?