There is no way to do this, because it is absolutely not Scrum, and makes sprints pointless. In a sprint, you commit to doing a set of stories. At the end of the sprint, you have either delivered each story or you have not. There is no partial completion, that's useless to the end-user, it's either done or it is not. So,…
-
Yes, for all three, but you will need an add-on to provide the authentication in the third one.
-
>it is going to run in the script console as it has to fill the field automatically whenever the users log work That's wrong. Are you really going to log in as an admin and run the script every time a user clicks "log work"? You should have a think about the field this data is to go into. If it's something the users should…
-
So, there is something wrong with the workflow, because the status of the issues does not change when you transition. You'll need to look at the workflow and probably the logs to work out why this is failing
-
Could you explain "somehow can't import it"? It does not tell us what is wrong with your import.
-
You need "move" permission to change the issue type inside a project when the source and target issue types have different configurations. Think of it as being the same as a "move but without selecting a new project"
-
If it is not done (because testing is not complete), then it is not done, so you do not burn down on it.
-
You will need to recover it from a backup
-
Boards are not containers for issues, they are a view of a set of them. To ge things to work the way you describe, edit the filters for the boards. The Kanban board filter should ignore issues that have got a status past "ready for dev" in the workflow, and the Scrum one should ignore anything before "ready for dev"
-
You can't. The index in Jira is rebuilt from the database. You can avoid re-indexing if you stop Jira and copy the index files over (do not attempt to put them on shared storage, it won't work)
-
Have a look at the "permission scheme" for the project. That tells Jira who can do what in a project.
-
Sorry for the delay. Off the shelf, you can't, you need add-ons to calculate numbers
-
Nope, that ability was removed a few months back. If it's bad enough (which I do think it is personally), your only option is to migrate to server, which will not be getting the new UI for a long time.
-
Exporting emails into a file based format does nothing to help you with this, and just makes your emails harder to use. The checking your users are asking for is a symptom of a broken process and a system set up to support something that's a waste of everyone's time. You should be looking to configure your system so that…
-
Anywhere that you have used the add-on will stop working. You'll get a small grey box noting the break in the content if you've used any of its macros, but everything else will work fine.
-
Have a look a the links Alana gave you, they cover that sort of thing
-
There's a few things most of us do: * Change the project name to include a (closed) type word * Change the permission scheme to one that allows only view, or no access at all if you want to have it hidden * Change the project category to "closed" or something, so you can say "and category != closed" in searches.
-
You will need to find or write a bit of code to do this. But I have a couple of sneaky ideas: ScriptRunner provides "web fragments" tied to scripts or built in functions. If you have that App, you could insert a web fragment that links to "new sub-task" in quite a few places My preferred trick - the sub-task panel has a +…
-
If there's nothing in the history, that implies the status did not change, or if it did, it went through a broken process to get there. How are you changing the status here? Does the transition have any customised post-functions?
-
There are times when I love the curious twists of the English language :-) For my distant youth, after I stopped eating meat, corn on the cob was often the only thing I could get at a barbeque, and everyone who cooked it wrapped it in aluminium foil, so it was basically baked. This works absolutely fine. Then I went to one…
-
No, you've not read the second paragraph of my last comment, where I've agreed with you and suggested a more simple way to do what you are looking for, while keeping the existing dashboard system simple and intuitive.
-
Best guess is that someone who can close it got tired of the same old arguments being repeated (I'm very guilty of repetetiveness in the face of people who ignore everything I'm saying, so I wouldn't be surprised if it was because of that) I've un-closed it. But I wouldn't waste your time with any more essays, it's not…
-
Atlassian are trying to standardise input on the core ASCII set to reduce the work having to be done with database collations etc.
-
No, you're falling into a very narrow mindedview yourself there. Think about it - product numbers, account numbers and other identifiers like that are not numbers, they are strings that happen to be constrained to numbers. If my bank account "number" was ABGORB32 it wouldn't be any better or worse than 71153622. If you…
-
No, I'm not missing the forest for the trees, I think it's you who is. You're ignoring the fact that we're looking at a forest and you want to report on the "current tree" without knowing which one it is. I don't want to create separate dashboards either, I totally agree with you. My ideal case would be to have project…
-
It's no good trying to push all the blame on the application either. This is a two part problem. First, you've got broken processes or demands causing fielditis. This disease you have is not just causing this one focussed problem, I can absolutely guarantee you it's causing problems across your reporting, your system usage…
-
Dashboards are not boards, and the question still stands, what project is the current one when your board filter is "project in X, Y, Z" I'd agree that it would be nice to have a "project dashboard" though, I'd locate them in projects myself, then you wouldn't need a selection at all.
-
I don't know. You need to look at why you "can't get all the issues under specific project". Can the REST user see them in the UI (i.e. check permissions)? Is there an error? What do the "missing" issues have in common that is different to ones that you can get?
-
On the board for the project, are Bugs you expect to be burning down in the far right hand column?
-
Actually, passwords are not encrypted, they're salted and hashed, but that's a technical quibble. It is possible to use encrypted databases and file-systems, but the software itself does not do it, it relies on the database and operating system to do the work when you need it.