Hi @Hoc All users should be able to see it, yes. Jacob @ NorthTEK Consulting
-
Hi @andrew.edwards This is something that you can change, here's how: * Click the "gear" icon, which is beside the Plan name * Go to Configure * Go to the "Dates" section * Click the drop down for "Due date " * Change to "End date" Hope this helps. Jacob @ NorthTEK Consulting
-
Hi @Rik007 You should be able to adjust the filter columns if you click the 3 dots that I circled in the image below: Hope that helps, let me know if it doesn't. Jacob @ NorthTEK Consulting
-
Hi @Chris Deutschmann If you're looking to configure the plan so that you start from a certain date, click the "Custom" date button beside the 3M, 1Y, Fit buttons and adjust the range so you can start from a certain date. Another thing you can do, though it's more work and depends on the fields you already have existing,…
-
Hi @Nate Looks like you got some good advice here but would like to chime in as I manage projects using JIRA and Advanced Roadmaps. If you create an issue, you can link it to other issues via the "Linked Issues" feature. This will allow you to link tasks to stories and show the dependancy of these tasks. You can also link…
-
Hi @Christophe Sutter Unfortunately, I don't think there's an elegant way to doing this without giving the vendor access to your JIRA instance. I manage projects using JIRA / Advanced Roadmaps and when I have tasks for vendors to complete, I'll add it as a task/epic and manage it myself. This way, at least I know I'll be…
-
Hi @Sunita Mathew I currently use Advanced Roadmaps for project management and it works well. When managing projects, Advanced Roadmaps allows you to create Plans that are project specific and will pull all related tasks into one plan where you're able to see the progress of every single task. This can be done for…
-
Hi @Jonas Kunze Not sure if this is something you resolved but there is an option to create custom date ranges on your Roadmap that goes back >1 year. You can create a custom date range by clicking the button beside "fit" on the Roadmap page. Hope that helps. Jacob @ NorthTEK Consulting
-
Hi @andrew.edwards Are you asking if it's normal for the Epic colour bar to be red but not the task bar? If so, this could be due to the way that you have the colouring set up. You can change it by "View settings" -> "Colour By" and configure it to what you'd like. Hope that helps. Jacob @ NorthTEK Consulting
-
Hi @Hoc, If you're a project admin, when you create a new issue type, you should be able to see the "Configure Fields" button like the below image: Click that and a window should pop up and show all of the fields that you can add to the ticket. Your custom fields should be there and un-checked. Check them and they should…
-
Have you tried logging in via SSO if your email has a gmail domain?
-
Hi Ranjani, I think it would work for now if you have a resource available to ensure quality, but I'm not sure that it would be scalable. My concern would be that if the workload increases such that having one person is not enough, you'll have to hire more and more people as the organization grows. An alternative would be…
-
Hi! I work for an org where we have projects per team (where some teams manage products), just some thoughts: * Can you get buy-in from everyone to populate the right information when creating epics/stories/etc so that your filters work properly? If they don't do it properly, do you have someone who will manage this and…